New customers

Information you need to become one of our customers

І. A request is submitted for the service „Request for survey of the conditions for connecting a facility to the electricity distribution network”.

 Documents required by the customer for “Request for survey of the conditions for connecting a facility to the electricity network”:

  1. A sketch with visa for a design for the facility or an approved by the respective Municipality a Detailed Site Development Plan (pursuant to art. 140 or art. 150 from the Territory Act) and an Order to legislate it.
  2. A document evidencing the ownership or the title to property.
  3. In case of tenancy contract –notary certified approval of the owner.
  4. A power of attorney to submit the request(if not in person).
  5. For business customers–a valid legal status of the company certificate (in case the company has not been re-registered); a copy of BULSTAT and court registration.
  • Copies of the above documents are acceptable!
  • The documents are submitted in person or by a person authorized before a notary!
  • Deadline for issuing a connection statement and a preliminary contract – 30 days.

ІІ. A request to be submitted for signing a „Connection contract”.

 Documents required by the customer for signing a contract for connecting a facility to the electricity distribution network:

  1. A permit for reconstruction of facility(for a facility intended for reconstruction).
  2. Construction permit in conformity to Ordinance №6and the Territory Act.
  3.  A permit for placing a portable facility, issued by the respective Municipality.
  4.  A copy of a statement/a preliminary contract.
  5.  A copy of draft designs –parts Electricity, including One-line diagram of Main distribution board and set fitting location, pursuant to a connection statement, architecture, water and sewage pipes and vertical planning.
  • Copies of the above documents are acceptable!
  • The documents are submitted in person or by a person authorized before a notary!
  • Deadline for contract preparation – 30 days.

ІІІ. A request for signing a „Contract for sale of electricity”.

 A contract for sale of electricity is signed after:

  • Signing a connection contract.
  • Payment of the connection price set in the connection contract.
  • Construction of connection equipment.

 

RESIDENTIAL CUSTOMERS ENCLOSE TO THE REQUEST!

  • Permit For Use Of The Facility

 

BUSINESS CUSTOMERS ENCLOSE TO THE REQUEST!

  • Permit for use of the facility.
  • Document evidencing title to facility.
  • Bulstat.
  • A legal status of the company certificate (if the company has not been re-registered).
  • Company decision.
  • Tax registration.
  • Deadline for rendering the service – 7days.